Red Dog Mine Life Extension Project

PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 31, 2026

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/09/2029

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The Red Dog Mine (RDM) is located in northwest Alaska, approximately 90 miles north of Kotzebue and 55 miles inland from the Chukchi Sea.  It lies within the DeLong Mountains of the western Brooks Range in the Northwest Arctic Borough. The Red Dog Mine Life Extension Project (RDMLEP) proposes to extend operations at RDM by developing the Aktiġiruq and Anarraaq ore deposits through underground long-hole stoping mining methods while maximizing the use of existing and permitted infrastructure within the project area. The Aktiġiruq and Anarraaq deposits contain critical minerals including zinc, lead, silver, and germanium and are located 9 miles and 7 miles northwest of RDM.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete