QTS Richmond Campus 5 (RIC 5) Data Center 5 (DC5)

PERMITTING DASHBOARD PROJECT POSTING DATE: APRIL 01, 2026

PROJECT WEBSITE: https://q.com/data-centers/richmond-5/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/11/2027

2 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Data Storage and Data Management

SECTOR
Data Storage and Data Management

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

QTS is proposing to expand the current approved limits of the QTS Richmond Technology Park Data Center 5 campus (RIC5). For the expansion, QTS is seeking authorization from the U.S. Army Corps of Engineers for impacts associated with the development of a data center building (referred to as DC5) and associated utilities, technologies, parking facilities, roads, and stormwater management facilities. The proposed data center building would be located near Richmond, Virginia. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete