Project Crucible
PERMITTING DASHBOARD PROJECT POSTING DATE: APRIL 22, 2026All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/30/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Manufacturing
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of War
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Section 408
Department of the Army, US Army Corps of Engineers - Civil Works
Tennessee
Description:
Project Crucible is proposed to be an integrated non-ferrous smelting and refining facility intended to produce 12 types of non-ferrous metals, including 11 of the 60 critical minerals designated by the US government, as well as semiconductor-grade sulfuric acid. Products include zinc, lead, copper, gold, antimony, gallium, germanium and semiconductor-grade sulfuric acid. The Project’s proposed location is in Clarksville, Tennessee adjacent to Crucible Zinc's existing smelting facility. The Project will receive feedstock primarily from U.S. and North American sources. Materials will arrive via multiple routes. The finished products are intended to be distributed to U.S. customers by rail and truck.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|