Plains and Eastern Clean Line

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016

PROJECT WEBSITE: http://www.plainsandeasterneis.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2017

13 out of 13

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Energy

LEAD AGENCY
Department of Energy, Office of Electricity Delivery and Energy Reliability

Description:

As of March 23, 2018, DOE and Clean Line Energy Partners have mutually agreed to terminate their Participation Agreement. NextEra Energy Resources has acquired Plains and Eastern Clean Line Oklahoma LLC and all of the assets for the transmission project in Oklahoma. For more information, see: https://www.energy.gov/oe/services/electricity-policy-coordination-and-…

Archived Project Description: Clean Line seeks the Department’s participation in the development, siting, construction, operation, maintenance, and ownership of high voltage direct current (HVDC) transmission facilities running approximately 705 miles from western Oklahoma to the Arkansas-Tennessee border (the Project). Clean Line, acting on its own and without the Department’s participation, would build additional facilities that would connect to the Project in Texas and Tennessee. The Project would deliver up to 4,000 megawatts (MW) of primarily wind generation from the Oklahoma and Texas Panhandle region to the mid-South and Southeastern United States, which could meet the annual energy needs of more than 1.5 million average American homes.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete