Lemhi Gold Project

PERMITTING DASHBOARD PROJECT POSTING DATE: NOVEMBER 20, 2026

PROJECT WEBSITE: Lemhi Gold Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, US Forest Service

Description:

The Lemhi Gold Project is an advanced-stage gold extraction mine located in Lemhi County, Idaho. The purpose of the Project is to develop, operate, reclaim, and close the gold mining operation using conventional open pit mining and mineral processing methods. The Project is located on public lands administered by the United States Forest Service (USFS), Salmon-Challis National Forest, North Fork Ranger District and controlled by Federal unpatented mining claims owned by Freeman Gold, and on private land owned by Freeman Gold. The mine boundary encompasses approximately 3,088 acres and includes the open pit, process plant, Waste Rock Storage Facilities (WRSFs), Filtered Tailings Storage Facility (FTSF), Overburden Storage Facilities (OBSFs), temporary low-grade ore stockpile, water management infrastructure, access and haul roads, power supply, and ancillary mine facilities. The Project proposes to mine approximately 47.4 million tons (Mt) of ore and generate approximately 188.9 Mt of waste rock material over an approximately 15.2-year operating life.