USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Larrea Solar Project

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 13, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Planned

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

The Larrea Solar project includes the construction, operation and maintenance, and decommissioning of an up to 205 MWAC photovoltaic solar facility and an up to 300 MW Battery Energy Storage System (“BESS”). The Project site would be on up to approximately 1,233 acres of federal land managed by BLM located in the Pahrump Valley in Clark County, Nevada and is located approximately 38 miles west of Las Vegas and southeast of the Town of Pahrump. The interconnect is planned at the Trout Canyon Substation at the intersection of SR-160 and Tecopa Road approximately 4.9 miles north of the site. All Project facilities would be located on lands administered by the BLM.