Harbor Island Seawater Desalination Facility

PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 11, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/26/2025

2 out of 8

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The Port of Corpus Christi Authority (the “Project Sponsor”) proposes to construct  a desalination facility on Harbor Island, near Port Aransas, Nueces County, Texas that will provide up to 100 million gallons per day (MGD) of product water with an anticipated discharge flow of 191.2 MGD based on 40% recovery of permeate water during reverse osmosis (RO) processing. Additional structures required to complete the facility are intake pumping and screening facilities, intake pipe, intake structure, Corpus Christi Ship Channel (CCSC) outfall and diffuser, Gulf of America (Gulf) outfall discharge tunnel pipe and diffuser. The intake and outfall pipes and associated structures will be constructed in the Gulf on State of Texas property. The discharge routes are via a concrete outfall pipe to a multi-port diffuser approximately 3.1 miles from Harbor Island out into the Gulf and an HDPE pipeline to a multi-port diffuser approximately 300 ft offshore on the south side of Harbor Island in Corpus Christi Channel. The Project proposes a new water supply for the Coastal Bend Region.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete