USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

G3 Expansion Project

PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 11, 2026

PROJECT WEBSITE: https://dtmidstream.com/ferc-project/g3/#documents

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/17/2027

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The project sponsor proposes to construct natural gas pipeline facilities composed of new, looped pipeline facilities and compression additions. Two separate pipeline loops are proposed in Illinois, totaling approximately 68 miles: the Joliet Loop and the Sycamore Loop. The Joliet Loop consists of approximately 42 miles of 36-inch-diameter pipeline loop in Kendall and DeKalb Counties. The Sycamore Loop consists of approximately 26 miles of 36-inch-diameter pipeline loop in DeKalb and McHenry Counties. The pipeline loops would be installed in parallel to the existing Guardian pipeline right-of-way. 

 

The project also involves the installation of two new natural gas compressor units at the existing Joliet Compressor Station, modifications to the existing Sycamore Compressor Station, construction of a new electric compressor station in Dodge County, Wisconsin, removal of existing controls currently restricting throughput capacity capability at Guardian’s existing Bluff Creek Compressor Station, as well as the construction of a new delivery meter station and other appurtenant pipeline facilities.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete