Desert Quartzite Solar

PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016

PROJECT WEBSITE: Bureau of Land Management Desert Quartzite Home Page

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/04/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Project would be located approximately 2.75 miles southwest of the City of Blythe, just south of the Interstate 10 freeway, in Riverside County, California.  The Project involves construction of a 450 MW solar facility and a 3 mile long 230 kilovolt transmission line that would connect with Southern California Edison’s Colorado Substation.  After construction, the Project would occupy up to 2,673 acres of BLM land and 154 acres of private land under the jurisdiction of the County of Riverside. Once completed, the Project would also include an operations and maintenance building, an on-site substation, internal access roads, and ancillary facilities. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete