Desert Charger Energy Project

PERMITTING DASHBOARD PROJECT POSTING DATE: FEBRUARY 14, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/26/2029

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Smith Blythe, LLC proposes to construct and operate an up to 450-megawatt (MW) solar photovoltaic (PV) power generating facility with an up to 300-MW battery energy storage system (BESS).  The Project is currently sited on approximately 3,305 acres of federal public land managed by the U.S. Bureau of Land Management (BLM) in Riverside County, California.  The Project will interconnect to the grid via a 1.5-mile 34.5 kilovolt (kV) collection line that will be stepped up to 230 kV into the Project substation.  Then, the Project will interconnect via 1-span 230 kV Gen-tie into the Southern California Edison’s (SCE) Colorado River Substation.    

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete