Contango Ore Johnson Tract Critical Metals Project
PERMITTING DASHBOARD PROJECT POSTING DATE: DECEMBER 01, 2025PROJECT WEBSITE: Johnson Tract Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/05/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Department of the Interior, National Park Service
Description:
The proposed project will extract copper, zinc, gold, silver, and lead through underground long-hole stoping complemented by backfilling of the stopes to mitigate the risk of surface subsidence. In addition to the mining infrastructure, there will be a year-round camp and site infrastructure will include roads, airport with IFR, and ancillary maintenance facilities. There will be no tailings or milling facility as the project proposes direct shipping of ore whereby the ore is mined, placed into sealed containers, transported to the coast and placed on barges for offsite processing. A barge loading facility will be established on port easement along the Tuxedni Channel of Cook Inlet.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|