Bluepoint Wind 1
PERMITTING DASHBOARD PROJECT POSTING DATE: DECEMBER 09, 2024PROJECT WEBSITE: https://bluepointwind.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Bluepoint Wind, LLC (Bluepoint Wind), the lessee of Renewable Energy Lease Area OCS-A0537 (Lease Area), proposes to construct and operate an offshore wind project in the western 42,429 acres of the Lease Area with associated offshore and onshore facilities. The purpose of the Bluepoint Wind 1 Project is to generate and deliver renewable energy from offshore wind to New York and/or New Jersey. The Wind Development Area is located approximately 43.7 statute miles off the New York coast and approximately 61 miles off the New Jersey coast. The Project will include up to 102 wind turbine generators with an anticipated capacity of up to 1.2 gigawatts.
The CPP and permitting timetable were due on February 7, 2025. BOEM has not submitted a CPP or comprehensive permitting timetable, which FAST-41 requires to be publicly posted within the statutory 60-day timeframe. BOEM is choosing to delay development of a permitting timetable until completion of the assessments outlined in the recently-issued Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects. The Executive Director will work with BOEM, when BOEM is ready, to attain compliance under FAST-41.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|