Bear Lodge Rare Earth Project
PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 20, 2026PROJECT WEBSITE: Bear Lodge Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/20/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of Agriculture, US Forest Service
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The Bear Lodge Rare Earth Project proposes to utilize the planned Bull Hill Mine, located near the town of Sundance in northeastern Wyoming, which is comprised of several disseminated deposits and characterized by a distribution of critical magnet rare earth elements (REEs), specifically neodymium-praseodymium (Nd/Pr), and other essential REEs. The Project includes the Bull Hill Mine (pit, ore hauling, waste rock storage, ore stockpile, ore crushing and loading, pit dewatering, and site management), grid supplied power, and access/transportation into and out of federal lands.
The project encompasses mining a USGS-recognized REE resource at the Bear Lodge deposit on Black Hills National Forest lands that will become feed material for a commercial processing facility to serve as a supply to downstream partners for permanent magnet manufacturing which are essential to defense and high-tech industries. The processing facility will be located on private land, approximately 40 miles from the mine area.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|