Aiya Solar Project (Moapa)
PERMITTING DASHBOARD PROJECT POSTING DATE: SEPTEMBER 22, 2016PROJECT WEBSITE: www.aiyasolarprojecteis.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs
Description:
The Aiya Solar Project proposes to construct a 100 megawatt solar generating facility on 900 acres of tribal lands on the Moapa River Indian Reservation (Reservation), in Clark County, Nevada. The solar generating facility is consists of photovoltaic (PV) solar panels on fixed-tilt or single-axis tracking systems, and associated equipment such as power inventers and transformers, collection systems, a substation, an operations and maintenance building with parking, meteorology towers and security fencing and lighting.
An approximately three-mile long, single overhead 230 kilovolt (kV) transmission line will connect the solar project to the existing NV Energy Reid-Gardner Substation located on lands administered by the Bureau of Land Management (BLM). A right-of-way across federal public lands managed by the BLM is necessary to link the facility and transmission lines on the Reservation with an existing substation and transmission line outside of the Reservation. The project is expects to take approximately 12 months to construct and have a project life of 25 years. The Moapa Band of Paiute Indians is supplying water for the project through a lease and will be delivering water via a new, two-mile long, above-ground pipeline on the Reservation.
The Bureau of Indian Affairs released the Final Environmental Impact Statement in March 2016 and the Record of Decision was signed on September 14, 2016. Since that time, the sponsor has elected to not pursue the project and it has been cancelled.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|