Yuba 70 (Segment 4 & 5)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/18/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
California
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans) proposes to improve safety, goods movement and emergency evacuation along the State Route 70 corridor. This segment of State Route (SR) 70 is in Yuba County, north of Marysville, between Post Miles (PM) 16.2 from Laurellen/SR 70 intersection and 25.8 (0.1 miles south of the Butte County line). The project proposes to provide a five-lane cross-section within the full postmile limits; PM 16.2 – 25.8. Two 12-foot travel lanes and 8-foot shoulder would be provided in each direction with a 14-foot wide continuous center Two Way Left Turn Lane (TWLTL) bounded by a minimum 20-foot Clear Recovery Zone (CRZ). The CRZ will incorporate side slopes of 4:1 or flatter and necessitate removal of any physical obstructions such as trees, utility poles, and other fixed objects.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|