World Trade Bridge Expansion

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/laredo/2024/world-trade-bridge…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/26/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

This project would involve widening the existing World Trade Bridge structure and constructing a new bridge downstream and parallel to the existing structure.  The new bridge structure will extend for a total of approximately 1,479 feet adjacent and parallel to the existing World Trade Bridge, from the International Boundary with Mexico (Rio Grande) to the International Port of Entry (POE). The project will require the acquisition of approximately 5.22 acres of new right-of-way along the south side of the existing bridge. This project will also require three temporary construction easements.  The first temporary construction easement is approximately 0.31 acres and located adjacent to the Rio Grande, just north of the existing World Trade Bridge. The second temporary construction easement would extend from the western terminus of Faskin Boulevard to the shore of the Rio Grande along the edge of the proposed new ROW.  This easement would be approximately 2.85 acres in size.  The third temporary construction easement is approximately 1.11 acres and located adjacent northwest from the western terminus of Faskin Boulevard, along the southbound lane of the existing World Trade Bridge. Together these three temporary easements would total approximately 4.27 acres and would only be utilized to facilitate the construction of the proposed project.  After construction is completed, these three temporary easements would revert back to their current landowner.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete