Walnut Ridge to Missouri State Line (Future I-57)
PROJECT WEBSITE: https://future57.transportationplanroom.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/04/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Arkansas
Description:
Project will complete future I-57 from Walnut Ridge, AR into southeast Missouri. The project alternatives are roughly 42 miles in length. The EIS will evaluate the environmental effects of all reasonable project alternatives and determine the potential impacts to social, economic, natural, and physical environmental resources associated with these alternatives. The project is needed because there is a gap in the system linkage that diminishes connectivity and mobility of the National Highway System. Additionally, there is a lack of reliable transportation infrastructure to support economic development and a need to enhance resiliency to extreme weather events along the route. Furthermore, Federal legislation designated
this high priority corridor as future Interstate Route 57 (I-57). The project’s purpose is to develop an interstate highway system that addresses the above-described needs while minimizing the negative impacts to the natural and social environment.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|