USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Virginia Street Bus Rapid Transit Extension

PROJECT WEBSITE: Virginia Street Bus RAPID Transit Extension Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/15/2018

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

A 1.8-mile extension to its existing bus rapid transit (BRT) service (the “RAPID”) operating in the Virginia Street corridor from its existing northern terminus at the 4TH STREET STATION transfer terminal in Downtown Reno to the UNR campus. The Project includes building fi ve new RAPID stations and upgrading three existing RAPID stations, right-of-way acquisition, exclusive bus lanes, traffi c signal priority at fi ve intersections, off -board fare collection, level boarding, and real-time bus arrival information at stations. Th e Project also includes the purchase of two 60-foot electric articulated buses, construction of two roundabouts at intersections to improve bus turning movements and enhance traffi c operations and safety, and sidewalk and crosswalk infrastructure improvements to enhance the pedestrian and bicycle network and visibility in the corridor. The boundaries of the 3.23-mile Virginia Street Bus RAPID Transit Extension Project are Plumb Lane/South Virginia Street to the south and the UNR Lawlor Events Center at approximately 15th Street/North Virginia Street to the north.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete