US 80 Widening in Kaufman County
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/03/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The proposed improvements consist of reconstructing US 80 from FM 460 in the City of Forney to Spur 557, and Spur 557 from US 80 to IH 20 in the City of Terrell, within Kaufman County. The proposed project would include an additional main lane in each direction and one-way continuous frontage roads in each direction with ramping improvements. The US 80/Spur 557 and Spur 557/IH 20 interchanges would be reconfigured with ramping and direct connector improvements.
Cross street intersection improvements are also included at FM 740/Pinson Road for approx. 2,000 feet, FM 548 for approx. 1,200 feet, Reeder Road for approx. 675 feet, Windmill Farms Boulevard for approx. 1,000 feet, FM 305 (Las Lomas Parkway) for approx. 1,800 feet, and FM 148 for approx. 1,300 feet.
Proposed improvements include tie-ins to side streets to the westbound side of US 80 at Lovers Lane, Mustang Boulevard, Trailhouse Lane, Marketplace Boulevard, Reeder Road, Irongate Boulevard, and Townsend Road; and to the eastbound side of US 80 to W. Broad Street, Elm Street, Cedar Street, Summerhaven, Regal Drive, FM 212, and Helms Trail.
The project would also construct a cul-de-sac at North McGraw Street to remove access to eastbound US 80 frontage road just east of Pinson Road.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|