US 51 Stoughton Road North (WIS 30 to I-39/90/94)
PROJECT WEBSITE: https://wisconsindot.gov/Pages/projects/by-region/sw/us51-corridor/northstudy.a…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/12/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The Wisconsin Department of Transportation (WisDOT) is evaluating reconstruction of US 51/Stoughton Road from WIS 30 in the city of Madison to Interstate 39/90/94 in the town of Burke, a
distance of approximately 5.2 miles. The purpose of the project is to accommodate existing and future travel demand with a focus on safety issues that affect travel on US 51 (Stoughton Road).The need for transportation improvements throughout the US 51 (Stoughton Road) North Study corridor is demonstrated through the following factors:
• Safety, including bicycles and pedestrians
• Travel Demand and Traffic Operations
• Roadway and Geometric Deficiencies
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|