US 380 Improvements in Princeton

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/dallas/2024/us380-princeton-09…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/27/2024

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The Texas Department of Transportation proposes to improve US 380 from Farm to Market Road (FM) 1827 to County Road (CR) 560 in within the cities of McKinney, Princeton, and Farmersville in Collin County, Texas, a distance of approximately 11.8 miles.  

The existing US 380 roadway would be widened and reconstructed as a freeway facility from FM 1827 to west of CR 337. From west of CR 337 to east of CR 458, the freeway would be on new location north of the city of Princeton, at which point it would rejoin the existing US 380 alignment and would be reconstructed as a freeway to CR 560 east of Lavon Lake.

The existing ROW width is approximately 120-160 feet. The existing ROW width at the existing Lavon Lake bridge is approximately 200 feet. The proposed ROW would be approximately 320-536 feet wide.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete