US 290 and SH 71 (Oakhill Parkway)
PROJECT WEBSITE: Oak Hill Parkway
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/21/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
TxDOT is currently conducting an environmental study for US 290 from State Loop 1 (SL1) to Ranch-to-Market Road (RM) 1826, in Travis County, Texas, a distance of approximately 3.6-miles. The study will also look at improvements to SH 71 from Silvermine Drive to US 290 in Travis County, a distance of approximately 1.2-miles. In addition, and as a result of public comment, the project includes a transition area along US 290 from FM 1826 to west of Circle Drive.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|