US 281/IH 69
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/12/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
To continue developing I-69 Texas, TxDOT is improving existing highway routes to interstate quality. US 281 in Premont is part of the I-69 Texas system, and before this road can be designated as an interstate, US 281 in Premont must be upgraded to interstate standards. To minimize overall impacts to Premont including homes and businesses, a relief route east of Premont has been identified as the preferred solution to upgrade US 281 in Premont to an interstate quality road. On Aug. 11, 2011, the Premont City Council passed a resolution supporting the east relief route option.
The proposed relief route will be built to interstate design standards and include:
- Four 12-foot-wide main lanes, two lanes in each direction
- four-foot-wide inside shoulders
- 10-foot-wide outside shoulders
- 48-foot-wide grassy center median
- Access roads in some locations to provide access to adjacent properties
-
Main lanes will accommodate 70 mph speed
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|