US 281 North
PROJECT WEBSITE: https://www.txdot.gov/projects/projects-studies/brownwood/us281-lampasas-evant…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/25/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The proposed project would construct an additional 12-foot-wide travel lane in each direction and separate the northbound and southbound travel lanes. Most of the corridor would include a 68-foot-wide grassy center median, 4-foot-wide inside shoulders and 10-foot-wide outside shoulders. Portions of the corridor where there is more development would include a 16-foot-wide flush median (two way left turn lane) and 10-foot outside shoulders. Several utilities will require relocation for the proposed project and improvements require the acquisition of additional right-of-way (approximately 570 acres). The proposed ROW width within the grassy median section would be 250-foot to 420-foot wide. The proposed ROW width within the flush median section would range from 160-foot wide to 260-foot wide. The most constrained area in the center of Adamsville would include the same 4-lane roadway section but with a 16-foot-wide flush median (two way left turn), curb and gutter, and 6-foot sidewalks.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|