US 101/SR 92 DIRECT CONNECTORS
PROJECT WEBSITE: District 4 Environmental Documents by County
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/26/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
Caltrans, in cooperation with the San Mateo County Transportation Authority and the City/County Association of Governments of San Mateo County, proposes to create a dedicated connection between SR 92 and the US 101 Express Lanes. Currently, there is no existing High Occupancy Vehicle (HOV) direct connector between US 101 Express Lanes and SR 92 that might provide incentives for carpool or bus use. Once completed, the project would provide better connectivity between the US 101 Express Lane and SR 92 to improve operational efficiency and encourage carpooling and the use of shuttles and buses.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|