US 101/Produce Avenue Interchange
PROJECT WEBSITE: https://www.ssf.net/departments/public-works/engineering-division/capital-impro…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/10/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) in conjunction with the City of South San Francisco and the San Mateo County Transportation Authority (SMCTA) are the sponsors of the United States (US) 101/Produce Avenue Interchange Project (the project) in the City of South San Francisco, within the County of San Mateo. The project would construct a new overcrossing of United States Highway 101 (US 101) in the City of South San Francisco. The new overcrossing, referred to as the Utah Avenue extension, would connect the Utah Avenue/South Airport Boulevard intersection on the east side of US 101 to San Mateo Avenue on the west side of US 101. The intersections of Utah Avenue/South Airport Boulevard and San Mateo Avenue would also be reconstructed to include turning lanes, and to connect to the new overcrossing by a through lane on San Mateo Avenue. The Airport Boulevard/Produce Avenue/San Mateo Avenue intersection on the west side of US 101 would also be modified or reconstructed.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|