University Boulevard Extension
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/31/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
The project would extend University Boulevard from Devlin Road to Wellington Road for approximately 2.5 miles and would be four lanes wide. At the north end of the project, the existing portion of University Boulevard would be widened from a two-lane undivided roadway to a four-lane, divided one (from approximately 650 feet south of the existing intersection of Wellington Road and University Boulevard to the southern entrance to Gainesville High School on University Boulevard). The new four-lane divided section would be built south from the southern entrance to Gainesville High School to the existing three-legged intersection of Devlin Road and University Boulevard, with intersection improvements as needed to accommodate the extension. The project would also include a 5-foot sidewalk on the west/south side of the roadway and a 10-foot shared use path on the east/north side. Additionally, turn lanes would be provided at specific locations, in coordination with existing and planned adjacent developments.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|