(TX) Toll 49 Segment 6

PROJECT WEBSITE: Toll 49, Segment 6

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/03/2028

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The project is sponsored by the North East Texas Regional Mobility Authority.

The limits of the proposed project are from the existing Toll 49 Segment 5 terminus at State Highway (SH) 110, southeast of Tyler, to U.S. Highway (US) 271, northeast of Tyler. The existing Toll 49 roadway extends from US 69 in northwest Smith County, approximately 25 miles southeast to SH 110.

There is no existing facility; therefore, the project is proposed on a new location. The proposed roadway will consist of an interim two-lane facility (one lane in each direction) with an intermittent single passing lane that alternates direction along the length of the corridor (Super 2) and an ultimate four-lane divided highway. 

The EIS will evaluate a range of build alternatives and a no-build alternative.  Possible build alternatives include three route options identified in the Toll 49, Segment 6 Feasibility Study  completed in November 2019. The three route options begin at the Toll 49, Segment 5 terminus at SH 110, end at different locations on US 271, and range from 10 to 13 miles long. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete