(TX) RM 620 at Anderson Mill Interchange project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/11/2026

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would add an elevated structure (overpass) that would function as a bypass lane in each direction through the Anderson Mill Road and El Salido Parkway intersections. The proposed improvements would also include adding turnarounds at both the Anderson Mill Road and El Salido Parkway intersections and constructing an additional right turn lane from northbound RM 620 to  eastbound Anderson Mill intersection. The proposed roadway would be separated by a variable width median, with curb and gutter. Bicycle and pedestrian accommodations would consist of a 10-foot shared use path, where feasible. In constrained areas along the roadway, accommodations would consist of either an 8-foot shared use path or a 6-foot sidewalk.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete