(TX) IH-35 Capital Express North
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/17/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The Texas Department of Transportation is proposing improvements to I-35 from SH 45N in Williamson County to US 290E in Travis County. The proposed improvements would add one non-tolled managed lane in each direction, reconstruct intersections and bridges to increase bridge clearances and east/west mobility, reconstruct the Wells Branch Parkway interchange to a diverging diamond intersection (DDI), and improve bicycle and pedestrian accommodations along I-35 frontage roads and at east/west crossings. Both the logical termini and limits of construction are at SH 45N and US 290. The project length is approximately 11.5 miles. The project would require the acquisition of approximately 17.0 acres of ROW, which would include approximately 10 to 15 feet of proposed ROW from various locations throughout the corridor.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|