(TX) IH 10 (from FM 2434 to US 90)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/15/2022

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Description:

The proposed facility would include a six-lane roadway, which includes; three 12-foot wide main lanes in each direction, 12-foot inside and outside shoulders, and two 12-foot wide, one-way frontage lanes in each direction. The proposed ROW width would vary, but would have an average width of 400 feet. 

The project would also include work on SH 71 from IH 10 to US 90, for approximately 0.7 miles North of IH 10. Work on SH 71 would include realigning/reconstructing the direct connectors from IH 10 to SH 71, within the center median area. No additional lanes are proposed on SH 71. 

The proposed facility would construct a new bridge (on a new alignment) crossing the Colorado River. The proposed bridge would be approximately 1600 feet, grade to grade. The bridge would most likely have 2 columns in the water, similar to the existing bridge. The new bridge would be 1 structure, east bound and westbound traffic would be separated by a raised concrete median.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete