(TX) FM 756 Paluxy Dr
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/07/2022
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
TxDOT Tyler District proposes to widen and reconstruct FM 756 from Jeff Davis Drive, south, to FM 344, in Smith County.
The proposed improvements include widening the existing two-lane roadway to a four-lane facility divided by a flush, two-way left-turn lane. The project also proposes a grade-separated intersection at FM 346.
The length of the project is approximately 6.8 miles. Within the project limits, FM 756 is classified as a major collector. Approximately 145.39 acres of new right of way (ROW) and 1.36 acres of temporary easements are required to accommodate the proposed improvements.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|