(TX) FM 518 (from SH 288 to FM 865)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/03/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The preferred alternative would reconstruct and widen the existing roadway from two lanes in each direction to three lanes in each direction.  The typical section would include two 12-foot-wide travel lanes and one 15-foot-wide outside travel lane (in each direction), a typical 18-foot raised median, and 5-foot-wide sidewalks on both sides of the roadway.  The project would convert the open ditches to a curb-and-gutter drainage system.  The preferred alternative would require approximately 25 acres of additional right-of-way.  The proposed right-of-way within this section would be approximately 150 feet.  The lane configurations (e.g. number of lanes) vary along the project limits to accommodate turning movements at various intersections and driveways. Improvements to cross streets (Walnut Street, Halbert Drive, and McLean Road) at the eastern project terminus are also proposed

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete