(TX) Denton County Outer Loop

PROJECT WEBSITE: The Regional Outer Loop in Denton County

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2027

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The project is a new location, limited-access freeway from I-35 in Denton County extending west across northern Denton County to connect to the Dallas North Tollway (DNT) in Collin County. The DCOL is proposed to be a 6-lane, access-controlled freeway with one-way frontage roads along each side within an average right-of-way width of 500 feet depending on the location and typical section. The typical freeway section would consist of three 12-foot-wide travel lanes in each direction, 12-foot-wide auxiliary lanes as warranted, 10-foot-wide inside and outside shoulders, two 12-foot-wide frontage road lanes on both sides of the mainlanes with a 10-foot-wide shared use path to the outside of the frontage roads. An open grassed median would separate the two sets of mainlanes and the frontage roads from the mainlanes.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete