(TX) Borderland Expressway

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/12/2022

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

Borderland Expressway Project (formerly known as Northeast Parkway Project), El Paso District
Project limits: On SL 375 East of Railroad Drive Overpass to FM 3255 Martin Luther King, Jr. Blvd. @ TX-NM
CSJ Numbers: 0924-06-136, 0924-06-320


The Texas Department of Transportation (TxDOT) proposes to construct an alternative route to Interstate 10 (I-10) through El Paso that meets the future transportation needs of the El Paso Metropolitan Area.  The ultimate design of the proposed Borderland Expressway Project (formerly known as the Northeast Parkway Project) is a 10.8-mile long, four-lane, limited access, new location facility within a 350-foot right-of-way (ROW) and includes five interchanges.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete