Tacoma Dome Link Extension Project EIS
PROJECT WEBSITE: Tacoma Dome Link Extension
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/12/2029
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Tacoma Dome Link Extension project proposed by Sound Transit would expand Link light rail from the Federal Way Transit Center in King County, Washington to the Tacoma Dome District area in Pierce County, Washington. The project is approximately 10 miles, and includes an elevated guideway and four new light rail stations in the following areas: South Federal Way, Fife, East Tacoma, and the Tacoma Dome District. Park-and-ride lots would be constructed at the South Federal Way and Fife stations. The project would provide a dependable and efficient connection along the corridor and respond to a growing number of transportation and community needs. In addition to build alternatives, the project will also consider a No Build alternative.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|