SUNBRIDGE PARKWAY ROADWAY US 192 TO NOVA RD

PROJECT WEBSITE: Sunbridge Parkway Extension Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/22/2026

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Florida

LEAD AGENCY
Florida

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

Osceola County is evaluating the extension of Sunbridge Parkway in northeast Osceola County, Florida. The Sunbridge Parkway Extension project is proposed to provide a new connection between US 192 (Irlo Bronson Memorial Highway), the southern project limit, and Nova Road (County Road [CR] 532), the northern project limit. It is anticipated that a four-lane divided corridor will be developed to accommodate the projected future traffic demand including pedestrians and bicyclists, requiring approximately 150 feet of right of way.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete