State Route 84 Real McCoy Fenders and Ramps Replacement Project
PROJECT WEBSITE: https://d4vpm3.wixsite.com/real-mccoy-ferry
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/12/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) is the NEPA Lead Agency for the State Route (SR) 84 Real McCoy Fenders and Ramps Replacement Project at post mile (PM) 2.49 in Solano County, California. Caltrans proposes to replace the existing timber fender system with a new steel pile fender system covered with rubber facing material, replace the boat ramps with new, longer ramps extending further into Cache Slough, and extend the deck of the ferry boat itself to improve vehicular access on and off the ferry. The proposed improvements would restore the structural integrity of the ferry deck, fender system, and boat ramps to improve reliability of the ferry and allow for the continued access to SR 84 across Cache Slough.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|