State Route 74 (SR-74) Lower Ortega Highway Widening

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-12/district-12-current-projects/sr…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/07/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The California Department of Transportation (Caltrans) proposes to widen State Route 74 (SR-74), also known as Ortega Highway, located in the City of San Juan Capistrano (City) and in areas of unincorporated Orange County. The total length of the project is 1.1miles (mi). The project proposes to widen SR-74 from two lanes to four lanes from Calle Entradero (Post Mile [PM] 1.0) to150 feet (ft) east of the City/County line (PM 1.9) with restriping from 150 ft east of the City/County line to Reata Road (PM2.1).

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete