State Route 1: San Antonio Creek Bridge Scour
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/21/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) proposes to prevent further scour
damage on the southwestern bent of the San Antonio Creek Bridge (Br. No. 51-0237 L/R),
located on State Route 1 at postmile 33.1 in Santa Barbara County. The project is set in
rural surroundings, with State Route 1 identified as a divided four-lane highway. The
proposed project is located approximately 12.0 miles north of the City of Lompoc.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|