SR91: Westbound Improvement Project
PROJECT WEBSITE: WB SR-91 Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2023
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans) District 7 and the Los Angeles County Metropolitan Transportation Authority (Metro), in collaboration with the Gateway Cities Council of Governments (GCCOG) and the Cities of Cerritos and Artesia, propose to widen and improve approximately 4 miles (mi) of freeway along westbound State Route 91 (SR-91) between approximately Shoemaker Avenue and the Interstate 605 (I-605) interchange, and at the I-605 northbound exit to Alondra Boulevard. The Study Area includes westbound SR-91 (Post Miles [PM] 16.9–19.8) and northbound I-605 (PM 5.0–5.8) and traverses the cities of Cerritos and Artesia.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|