SR 30 (US 98) FROM SR 189 BEAL PKWY TO WEST END OF BROOKS BRIDGE

PROJECT WEBSITE: Around the Mound Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/02/2026

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Florida

LEAD AGENCY
Florida

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior

Description:

This Project Development and Environment (PD&E) Study evaluates options for rerouting State Road (SR) 30 (US 98) Miracle Strip Parkway “Around the Mound” in Fort Walton Beach, Florida. The length of rerouted SR 30 (US 98) would be 0.71 miles as compared with the existing linear distance of 0.61 miles.  The project limits are on US 98 from SR 189 (Beal Parkway) to West End of Brooks Bridge and North along SR 85 (Eglin Parkway) to Hollywood Boulevard

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete