SR 275 Norfolk to Wisner

PROJECT WEBSITE: https://dot.nebraska.gov/projects/future-projects/norfolk-wisner/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/17/2026

6 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

No icon

LEAD AGENCY
Nebraska

Other Agencies with Actions or Authorizations:

Department of Transportation

Department of Transportation, Federal Highway Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The project, known as Norfolk – Wisner, would take place approximately 0.25 miles east of the junction of US-275 and Nebraska Highway 57 and extends east and south to approximately 0.25 miles southeast of Wisner, Nebraska. The project would expand approximately 15.5 miles of the existing two-lane highway on US-275 to a four-lane expressway by constructing a new, parallel two-lane roadway on one side of the existing US-275.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete