SR 138 Northwest Corridor Improvement (I-5 to SR 14)

PROJECT WEBSITE: Northwest 138 Corridor

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

California

LEAD AGENCY
California

Description:

In 2013, the California Department of Transportation (Caltrans) in coordination with the Los Angeles County Metropolitan Transportation Authority (Metro) initiated the Draft Environmental Impact Statement/Report (Draft EIS/EIR) for the Northwest 138 Corridor Improvement Project (Northwest 138 Corridor). 

The environmental document evaluated corridor will evaluate corridor alternatives and related operational improvements such as improving sight distances and bringing non-standard roadway features up to current design standards. The Northwest 138 Corridor extends approximately 36 miles along State Route (SR-138) between Interstate 5 (I-5) and State Route 14 (SR-14) in Los Angeles County. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete