S.R. 0034-060 Safety Improvements and Resurfacing Project and S.R. 0034-059 Spring Road Bridge

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The project is approximately 6.9 miles in length, beginning just north of the Sterretts Gap Roundabout, located at the Perry/Cumberland County line, extending north through the community of Shermans Dale, and ending at the intersection of S.R. 0034 with S.R. 2003 (Mountain View Road) and T-412 (Rambo Hill Road). The project includes safety improvements at the following five (5) intersections:
• S.R. 0034 and T-303 (Fox Hollow Road)
• S.R. 0034 and T-306 (Youngs Church Road)/T-308 (Richwine Road) 
• S.R. 0034 and S.R. 2001 (Windy Hill Road)
• S.R. 0034 and Old Mill Road (T-325) 
• S.R. 0034 and S.R. 2003 (Mountain View Road)/T-412 (Rambo Hill Road) 
The resurfacing portion of the project from the Sterretts Gap roundabout to Sherman Creek includes drainage improvements, guiderail updates, tree trimming, slope stabilization, base repair and milling in curbed areas. 
The project will also include replacement of the structure carrying S.R. 0034 over a tributary to Sherman Creek (BMS 50003400900050 / BRKEY 29498), located just north of the intersection with Old Mill Road. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete