USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Spur 399 Extension

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/29/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would extend Spur 399 from US 75 to US 380, as a new location facility. The Spur 399 Extension would be an eight-lane, access-controlled freeway with one-way frontage roads on each side within an anticipated right-of-way width ranging from 165 feet to 696 feet, with an average ROW width of approximately 400 feet, depending on location. 

Frontage roads would be provided along the mainlanes starting near Airport Drive and extending the remaining length of the Orange Alternative/Preferred Alternative to connect to US 380. No frontage roads would be provided from SH 5 to Airport Drive as existing FM 546 would serve as the frontage road in this section. 

The primary travel lanes would be elevated (on bridge/viaduct) along much of the proposed facility to minimize impacts to utilities, water features and floodplain. Other areas would be constructed on an earthen embankment. 

The freeway facility would also include ramps, shared-use paths along the frontage roads, and would connect to arterial roadways to support existing roadway network connectivity. Grade-separated interchanges would be constructed at Airport Drive/FM 546 and CR 722/Enloe Road and grade separations would be provided at CR 317/FM 546 and FM 546. An at-grade signalized intersection would connect the Spur 399 Extension to US 380.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete