USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

SpaceX Starship-Super Heavy Project at Kennedy Space Center Launch Complex 39A

PROJECT WEBSITE: https://www.faa.gov/space/stakeholder_engagement/spacex_starship_ksc

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/06/2026

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The Federal Aviation Administration (FAA) as the lead Federal agency is preparing an Environmental Impact Statement (EIS) to evaluate the potential environmental impacts of issuing a new of modifying an existing commercial launch vehicle operator license to SpaceX for the Starship-Super Heavy launch vehicle at Launch Complex 39A (LC-39A) at Kennedy Space Center (KSC), Florida. SpaceX proposes to construct launch, landing, and other associated infrastructure at and in proximity to LC-39A. The proposal also includes Starship-Super Heavy launches at LC-39A; recoverable Super Heavy booster and Starship landings at LC-39A or on a droneship; and expendable Super Heavy booster and Starship landings in the ocean.  

SpaceX must obtain a new or modification of an existing vehicle operator license from the FAA for Starship-Super Heavy launch and landing operations. Issuance or modification of a vehicle operator license and approving airspace closures is considered a major Federal action under the National Environmental Policy Act (NEPA). In consideration of SpaceX’s revised proposal, National Aeronautics and Space Administration (NASA) and FAA have determined that an EIS is the appropriate level of NEPA analysis to address the adjusted scope of Starship-Super Heavy at LC-39A. SpaceX has prepared the EIS under the supervision of the FAA which is serving as the lead agency at NASA’s request. While the 2019 Environmental Assessment (EA) prepared by NASA provides an analytical baseline, the environmental impacts of these proposed changes to Starship-Super Heavy LC-39A development and operations will be specifically analyzed in this EIS. 

The EIS considers the potential environmental impacts of the Proposed Action and the No Action Alternative. The successful completion of the environmental review process does not guarantee that the FAA would issue a new or modification of an existing vehicle operator license. The project must also meet all FAA safety, risk, and indemnification requirements for the appropriate license.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete