SH 249 Superstreet

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/11/2024

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would widen SH 249 between the construction limits from six lanes to eight lanes with curb and gutter. The proposed SH 249 roadway would consist of four lanes: a 13-foot-wide inside lane, two 12-foot-wide middle lanes, and a 13-foot-wide outside lane in each direction. Directions of travel would be separated by a raised median varying from 6 to 30 feet wide. Turn bays for left and right movements would be added at major intersections. Ten-foot-wide sidepaths would be constructed on both sides of the roadway near the ROW limits. The proposed ROW would be approximately 162 to 180 feet wide. The proposed improvements would require approximately 30.98 acres of additional ROW.  Additionally, storm sewer facilities, three detention ponds, and intersection improvements are proposed.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete