SEIS - Juneau Access Improvements Project
PROJECT WEBSITE: Juneau Access Improvements
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/18/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
New highway construction
The Juneau Access Improvements (JAI) Project is a proposed action by the Federal Highway Administration (FHWA) and Alaska Department of Transportation and Public Facilities (DOT&PF) to improve surface transportation to and from Juneau, Alaska, within the Lynn Canal corridor. The purpose of and need for the Juneau Access Improvements Project is to provide improved transportation to and from Juneau within the Lynn Canal corridor that will reduce travel times, state and user costs while providing capacity to meet demand and improved opportunity to travel.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|