Scranton Beltway Project, Clarks Summit and Wyoming Valley Interchanges

PROJECT WEBSITE: https://www.paturnpike.com/traveling/construction/site/scranton-beltway

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/14/2027

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The Pennsylvania Turnpike Commission (PTC) and PennDOT seek to provide direct connections between the Northeast Extension (1-476), a toll road and Interstate 81 (I-81) in the Scranton, PA area (Luzerne and Lackawanna Counties). I-81 is currently over utilized and frequently congested during morning and afternoon peak hours. The Northeastern Extension provides an alternative route to I-81 from Wyoming Valley (Interchange 115) to Clarks Summit (Interchange 131) but is underutilized compared to I-81. As a result, the PTC performed preliminary engineering tasks for a potential Scranton Beltway Project which would include direct connections between I-476 and I-81. It is projected that the proposed improvements will benefit both the PTC and the PennDOT as diverted traffic will improve operations and congestion on I-81 and increase utilization on I-476. The proposed improvements consist of new, direct connections at the external locations of Wyoming Valley (Milepost A-115 to A-116.2) and Clarks Summit interchanges (Milepost A-129.8 to A-130.4).

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete